This note describes the process of moving code into a live site.

The process of moving code to production is intended to minimize the risk of damaging the production site. It is the responsibility of the Site Administrator to ensure that adequate testing is performed in the staging area before moving code to production. The process follows the steps below.
  1. Once it has been tested successfully, the staging site is remounted read-only, to avoid accidents.
  2. The filestorage for the production site is backed up on the filesystem.
  3. A Core Developer works from the staging log to update production. The Core Developer performs tests on the production site.
  4. The catalog on the production site is refreshed.
  5. The production site storage is packed.